3M tape in India: from a 150-day wait to delivery in 24 hours

Twenty vendors reported no stock. One follow-up uncovered two A4 sheets in a supplier’s R&D lab—enough to move the customer’s prototype forward.

Twenty qualified vendors. The same answer from every one: at least 150 days.

A US-based consumer hardware company that has an arm in India needed a specific 3M tape for prototyping and design. The vendors Latch contacted reported that they did not hold it in stock in India. Their quoted lead times put the material roughly five months away.

Latch kept following up. One vendor eventually found two A4 sheets in his R&D lab. The company received the tape within 24 hours, without having to buy a full roll or meet a minimum order quantity.

The breakthrough came from finding the quantity the prototype needed in a place a standard stock enquiry would miss.

How a small procurement requirement becomes a large project delay

A prototype can be nearly ready and still depend on one missing material. When that material carries a long procurement lead time, the effect reaches beyond the purchase order: a test may have to move, a design decision stays open, and the next iteration has to wait.

For procurement teams, even tape can be an engineering requirement. Choosing an adhesive involves the assembly, materials, manufacturing process, and conditions it must withstand. 3M’s adhesive and tape selection guidance explains why the application matters when selecting a bonding solution.

That makes “buy something else” a decision for the engineering team. Procurement first needs to establish whether the specified material can be obtained on a useful timeline.

In this case, all 20 qualified vendors initially pointed to the same obstacle: a minimum 150-day lead time.

The follow-up that found two A4 sheets

One vendor had left a small opening: he would check and get back to Latch.

Latch’s procurement agent followed up. The vendor estimated there was a 99.9% chance he would not find the tape. But there was one place he could still look: his R&D lab.

He checked. There were two A4 sheets.

There was no roll available to buy. There was no minimum order quantity to satisfy. For this prototyping requirement, the sheets provided a way forward that the standard supply route had not offered.

RequirementInitial supplier responsesOutcome with Latch
Specific 3M tapeNo Indian stock reported by the 20 vendors contactedTwo A4 sheets located in a vendor’s R&D lab
TimingMinimum 150-day quoted lead timeDelivered within 24 hours
Purchase quantityStandard supply route unavailable on the required timelineNo full-roll purchase or MOQ required

What faster delivery changed for the hardware team

The immediate result was concrete: the team had the requested tape in hand within a day instead of facing a quoted wait of at least five months.

That removed this material shortage as a barrier to the next prototyping step. It gave the company a way to continue working with its specified tape, without making a material substitution simply because the usual supply route was slow.

The small quantity also mattered. Buying for an experiment and buying for production are different requirements. Two sheets could address the immediate prototype need without requiring a full roll.

These are the practical benefits of procurement built around hardware development: obtain the material needed for the next engineering milestone, in a usable quantity, on a useful timeline. The 24-hour result applies to this delivery; it does not establish an ongoing supply of production volumes.

How to reduce procurement lead time when suppliers report no stock

This case offers three useful questions for teams facing a long lead time:

  1. What quantity does the next milestone actually require? A sample or sheet may be sufficient for a prototype, even when a production pack is unavailable.
  2. Does the supplier have access to material outside regular saleable inventory? In this case, the relevant stock was in an R&D lab.
  3. Which open conversations deserve another follow-up? A supplier who offers to check has left a sourcing path unresolved.

An AI procurement agent can help carry that coordination forward. Here, the decisive action was following up on a vendor’s offer to look again.

Twenty initial responses pointed to 150 days. One completed follow-up uncovered two sheets and made a 24-hour delivery possible.

Have a hard-to-find material holding up a prototype? Tell Latch what you need, including the specification, minimum usable quantity, and required delivery date.