How a physical AI team implemented three projects in the time planned for one

Latch delivered 34 SKUs within 15 days, with most arriving the same day or within 48 hours. The team’s US sourcing options had quoted four to eight weeks.

A physical AI company developing intelligent systems for robots and humanoids needed 34 distinct items. Its US sourcing options carried lead times of four to eight weeks.

Latch sourced and delivered all 34 SKUs within 15 days. Most arrived the same day or within 48 hours; the fabricated product took 15 days.

With those requirements fulfilled, the company implemented three projects in the timeline originally planned for one.

Why physical AI development depends on procurement speed

Physical AI brings intelligence into systems that interact with the real world. NVIDIA’s overview of humanoid robotics describes development spanning training, simulation, and deployment on physical robots.

For teams building those systems, progress eventually depends on physical hardware being available. Software and simulation can advance while parts are on order, but assembly and physical testing require the relevant components.

This makes physical AI procurement part of the development schedule. A long wait for a required item can push back an integration step and the learning that follows it.

With 34 SKUs to source, there are also 34 distinct requirements to resolve. A stock-keeping unit, or SKU, identifies a distinct item; it does not tell us how many individual pieces were ordered. Each requirement needs a clear specification and a workable delivery timeline.

The result: 34 SKUs delivered within 15 days

The company’s requirement included a fabricated product alongside the other items. Latch fulfilled the complete set within 15 days, with most items delivered substantially sooner.

MeasureCustomer’s sourcing contextLatch outcome
Scope34 SKUsAll 34 sourced and delivered
Timing comparisonFour-to-eight-week lead times through the US options consideredComplete set delivered within 15 days
Most itemsPart of the same sourcing requirementDelivered the same day or within 48 hours
Fabricated productRequired fabricationDelivered in 15 days
Project implementationTimeline originally planned for one projectThree projects implemented in that period

The four-to-eight-week figure describes the sourcing options in this engagement. Lead times vary by component, supplier, quantity, and availability.

Why early component deliveries matter

A bill of materials can contain items with very different availability. Treating every line as if it shares the longest lead time hides opportunities to start work sooner.

In this engagement, most items arrived the same day or within 48 hours, while fabrication took 15 days. Early deliveries can allow a hardware team to prepare, assemble, or test the portions of a system whose dependencies are already available. Whether that work can begin depends on the design and project plan.

The confirmed business result here was that the company implemented three projects in the time allocated to one. Faster procurement helped make that possible by bringing the required hardware into the team’s hands sooner.

For robotics and automation teams, that is a useful way to assess procurement performance: alongside price and order status, track when materials become available for engineering work.

What other robotics teams can take from this case

When preparing a multi-item sourcing request, make the project dependencies visible:

  • Identify which items unlock the next build or test. These deserve particular attention when delivery dates slip.
  • Separate fabricated products from readily available components. Their timelines and supplier questions will differ.
  • Record required delivery dates at the item level. A single date for the whole order can obscure which work could start earlier.
  • Compare sourcing routes against the actual specification. Price, availability, quantity, and technical fit belong in the same decision.

These practices help hardware procurement teams connect supplier activity to project implementation.

For this physical AI company, the outcome was 34 SKUs delivered within 15 days and three projects implemented in one project’s planned window. Procurement speed translated into more completed work.